Heavy equipment is back on the site of a new landfill being built north of Boissevain.

 

The landfill will service the town and RM of Morton. Reeve Bob McCallum says construction was delayed due to permit issues with some provincial water departmtents.

 

He says clearance has been obtained so work can resume.

 

 

McCallum hopes one of the holding cells can be built this fall so the municipalities can start using the new landfill.

 

The Reeve doesn't think the 7-week delay will add any additional cost to the project.